Wing Avenue residents could get relief from public utility costs depending on final plan

Wing Avenue north of 60th Street

By Joanne Bailey-Boorsma

joanne@wktv.org

 

At a recent December workshop, residents along Wing Avenue got a little bit of good news — the city would defer most of the costs for public utilities.

 

In November, the Kentwood City Commission approved an amendment allowing for a farmhouse exemption with a property owner only having to pay the first 125 feet of frontage for installation of water and sewer. The rest would be deferred if the parcel were split in the future.

 

“Currently, many of these homes along Wing Avenue were looking at upwards to $90,000 to hook up,” aid Kentwood City Engineer Tim Bradshaw. “It brought the cost of hooking up to sewer and water down to a more reasonable price and made it comparable to having a well or septic.”

 

It was noted at a Dec. 5 workshop that based on City of Grand Rapids’s current rates, the connection costs for a 125-foot frontage would be about $17,050 for sewer and $15,975 for water. Those costs are only paid upon connection. According to Building Advisor, the cost of installing water and septic can be $20,000 or more.

 

Another cost concern was that of sidewalk and storm sewer construction. The City Commission also recently amended the city policy to no longer assess for those items if the improvements are included in the final design of Wing Avenue. Residents, however; would be required to maintain the sidewalks running along their property.

 

Wing Avenue at 60th Street

Bradshaw said at the recent workshop, residents seemed to respond well to the changes since it did reduce some of the cost concerns, however; there are still several other issues residents have including keeping the natural feel and look of the road. Impact on the trees and the natural features lead several residents to petition the city to consider designating Wing Avenue from 52nd Street to 60th Street as a Natural Beauty Road in accordance to the guidelines established by the state legislature in 1995.

 

Michigan’s Natural Beauty Road Act is designed to identify and preserve certain county-local roads that have unusual or outstanding natural beauty by virtue of native vegetation or the natural features. There are 34 roads in Kent County with the designation, none of which are in Kentwood.

 

There are several requirements including that the speed be not more than 35 mph. Wing Avenue’s current speed limit — which is determined by a Michigan State Law — is 40 mph.

 

The designation would not prevent tree removal when necessary for the safety and protection of the traveling public and vehicles, including improvements to the roadway and for public utility construction crossing Wing Avenue. Tree removal would not be allowed for construction of public utility alongside the road.

 

The Kentwood City Commission will consider the Natural Beauty Road petition at its Feb. 7 meeting. This is after the presentation by the consulting firm Fleis & VandenBrink on its final corridor study which is scheduled for Jan. 17. Fleis & VandenBrink have been tasked to study several items including public utility planning, road construction, and non-motorized needs such as sidewalk, bike lanes, etc.

 

At the December workshop, the consulting company indicated it would likely recommend the construction of 11-foot lanes striped at 10 feet for safety, better speed control, reduce cost and reduce tree impact over the standard 12-foot width. Also, it was indicated to use the speed of 40 mph to improve sight distances. The firm was still reviewing curb versus ditches and sidewalks/non-motorized trails.

 

The City Commission is expected to make a final decision on the Wing Avenue plans at its Feb. 21 meeting. Once the final scope has been determined, engineering and design work will begin. Bradshaw said the city has targeted the spring of 2018 to start construction.

Meeting tonight on Kentwood’s progress on Wing Avenue

Wing Avenue at 60th Street
Wing Avenue at 60th Street

It’s only a mile long so you would think it would be fairly easy to put together a plan to reconstruct Wing Avenue.

 

But there are a number of variables when dealing with Wing Avenue, said Kentwood City Engineer Tim Bradshaw, such as slope, speed, trees, drainage, future growth and utilities along with who would be the best to provide those utilities as the road serves as a boarder to Grand Rapids and Kentwood.

 

It is why the City of Kentwood has spent the past couple of months meeting with residents, gathering input and collecting data focused on putting together a plan for Wing Avenue. A second meeting to discuss this plan is set for 7 p.m. tonight at Kentwood City Hall, 4900 Breton Road SE.

 

“The condition of the road has gotten to the point that there is not much more the city can do to maintain it,” Bradshaw said, adding even snowplowing has become a challenge along the road due to the ditches. Wing Avenue also serves as the main artery between 52nd and 60th streets with no relief from that unless Breton Avenue is ever extended to 60th Street.

 

Wing Avenue north of 60th Street
Wing Avenue north of 60th Street

There also is potential for future development in the area which would add more traffic to the road, Bradshaw said.

 

Earlier this year, the city hired the consulting firm Fleis & VandenBrink to conduct a corridor study and assist with gathering public input. This included hosting a meeting in August where about 80 residents from the 92 homes that were notified attended. Bradshaw said there about 60 properties on Wing Avenue with about 30 or so on Paris Park Drive that have properties that back up against the road. All were notified of the plans to work on Wing Avenue.

 

“We hire a consultant to work with us based on the previous conservations with property owners who had mixed amount feelings on what should be done.” Bradshaw said. “Each has a passion with them. Some really like the rural feel of the road, others had safety concerns and others wanted to protect as many trees as possible.”

 

The residents along Wing Avenue have well water and septic as there are no current water or sewer lines or storm sewer. There has been discussion of adding such utilities, which could spur development, Bradshaw said.

 

Over the past couple of months, Fleis & VandenBrink and the city have looked at the trees to see how many could be saved along with getting traffic counts especially with school in session. The speed limit along the road, which currently is 40 mph, is mostly set by the state, Bradshaw noted.

 

The goal of the City of Kentwood is to have the study of the road completed by the Dec. 6 City Commission meeting. Design and engineering work on Wing Avenue is expected to take place next year with construction beginning in 2018.