Two businesses approved to be ‘anchor tenants’ at Kent County Sustainable Business Park

Kent County Land for planned Sustainable Business Park, aerial shot that includes the property adjacent to the landfill, with the landfill in the background. (Kent County)

By WKTV Staff

ken@wktv.org


Kent County has announced that a Project Development Agreement has been approved for an “anchor tenant” at the county’s planned Sustainable Business Park in Kent County’s Byron Township, southeast of Byron Center, with the Department of Public Works set to “work with” Continuus Materials and Anaergia on “developing landfill alternative” businesses.

According to a Monday, March 7, statement, late last week the Kent County Board of Public Works approved a Project Development Agreement (PDA) with Kent County Bioenergy Facility, a joint venture between Continuus Materials and Anaergia, and the agreement is now fully executed.

The two companies partnered on a response to a Request for Proposals from Kent County for an “anchor tenant” at the Sustainable Business Park which is planned for 250 acres adjacent to the South Kent Landfill in Byron Township.

For a previous WKTV story on the planned Sustainable Business Park, visit here.

Dar Baas, director of the Kent County Department of Public Works, (center in yellow vest) discusses the proposed Kent County Sustainable Business Park in Byron Center with Liesl Eichler Clark, director of the Michigan Department of Environment, Great Lakes and Energy, (Center in orange vest) on a tour in October 2021. (Kent County)

According to the announcement, the PDA is the next step in developing a “multi-faceted mixed waste processing facility capable of handling 430,000 tons of municipal solid waste and recyclables each year to produce renewable natural gas, fertilizer, and recyclable commodities.”

Anaergia has a “proven track record” on four continents of turning organic waste into renewable natural gas and fertilizer using high efficiency anaerobic digestion, according to the announcement. Continuus Materials will produce a roof coverboard material, called Everboard, on site from low value plastics and paper. The plan calls for other recycling and waste processing companies to locate around the anchor tenant at the future Sustainable Business Park.

“We are excited to take the next step in a public-private partnership to help us achieve our goal of diverting 90 percent of trash from the South Kent Landfill by 2030,” Emily Brieve, chair of the Kent County Board of Public Works, said in supplied material/ “Approving the PDA is the culmination of several years of evaluation and due- diligence to find the right company that was a good fit for our community with proven technology. Now the real work begins to nail down costs, schedules and site plans.”

The PDA will guide the DPW and Kent County Bioenergy Facility over the next 18 to 36 months until the project can be fully contracted and financed. If all goes as planned, the facility could be up and running in about three years. The PDA process will also include “continued stakeholder involvement” in the project and to develop supporting policy.

The plan currently calls for Kent County to make a $70 million investment through a bond that would be repaid by tipping fees and shared revenue from materials produced at the park.

Kent County Bioenergy Facility would invest an estimated $280 million and operate the facility. The State of Michigan recently allocated $4 million in the 2021-22 budget toward an estimate $19 million of necessary site preparation and infrastructure.